JOCA paralyzes the works of the Auditorium because it wants to increase the budget

May 15 from 2018 - 16: 41

Since last March, the works of the Xàbia Auditorium have been halted by the construction company, JOCA Engineering and Constructions. Although in a first assessment, it was suggested that the works were going to continue after the Holy Week celebrations, it was not like that.

After about two months without moving machinery and land, the Javea Town Hall regrets the evident delay that takes the execution of the municipal auditorium theater and that the construction company is not complying with the schedule of deadlines presented to the construction management.

According to they have affirmed from the consistory, "In the last months there are already several changes that this company has suggested regarding the initial project, all aimed at increasing the budget or its profit margin."

Before this action, the executive Xabi rejected frontally any modified and emphasizes that "When he offered the construction of the auditorium, he did so with a budget of 3,3 million euros. It was JOCA Ingeniería y Construcciones who voluntarily reduced this budget to 2.4 million and was forced to build it in these economic conditions."

At the moment, according to municipal sources, the construction company has not formally notified that it is going to desist from the work, although the current sensation, from the consistory, is negative and generates serious doubts.

The councilman of Culture, Quico Moragues, has been especially affected by the blockade of the theater auditorium and the lack of responsibility that the company is demonstrating. "It is a project in which both the Corporation, citizens and cultural groups have much enthusiasm deposited and the most important cultural level of recent years in Xàbia", said Moragues, therefore, it is planned to convene the Culture Council to inform them of how the situation is evolving.

Also, the mayor hopes that both the City and the company, JOCA, reach an agreement in the coming weeks and works resume, "Without that it means putting more euro or reducing the quality of the project", the councilor insisted.

Given the action that the City Council can take on this situation, it should be noted that it can not act hastily, since it is the Law that specifies the steps and deadlines to be followed in this type of situation, both when awarding and leaving without effect a contract. However, the same sources assure that an exhaustive follow-up of the company's procedures is being carried out and all necessary means will be used to defend the interests of the neighbors of Xàbia, as well as to demand the corresponding responsibilities.

Comments
  1. ARA XÀBIA says:

    Look what ho vam warn… Madrid, Alcanyis… col.legis mig fets, implicats in cases of corruption and 'double invoices' at the Lezo operation… attended to JOCA, i res… ho vam send by electronic mail to all the regidors d 'Ajuntament de Xàbia (Marta, Miragall, Moragues, Paco Torres, Zamora, Segarra, Mayor's Office ...) dies abans, fins i tot al register of the Generalitat Valenciana! I res. Eixa rebaixa was clear that it was a temerity, that they acted as solen fer en moltes obres. Ara neither dinés nor audi. A 10 to the gestió senyors!

  2. Fco Javier Garde says:

    It is clear that they lowered the initial offer. If they are not able to perform the Auditorium for the assigned price that DISISTAN and the citizens do not pay the consequences.

  3. ARA XÀBIA says:

    Millor will not say res ... but, the members of the table are going to inform me of who they contract? Are you going to ask about the reliability of the JOCA company? Do you know that ja has deixat 'penjat' to various administrations? Yes, you know… but you are only going to look at the numbers i «a la baixa» temerària. Pity, to pay, always, the poble de Xàbia, is to dir, tots.